Analyze how each machine is being used within its defined limits.
Type:
Tutorial
Length:
3 min.
Transcript
00:04
To optimize the efficiency of your layout in Factory Design,
00:08
you can analyze how each machine is being used within its defined limits.
00:12
Based on the analysis, you can make changes to the layout and review the effects on utilization.
00:18
To follow along with this tutorial, from the Quick Access Toolbar, click Open,
00:23
navigate to the Tutorial 4 folder, and open Material Flow Analysis_Complete.dwg.
00:30
From the ribbon, Factory tab, Material Flow panel,
00:34
expand the Transportation drop-down and select Machine.
00:38
This activates the Machine Utilization Meters.
00:42
If the Machine Utilization indicator is not visible, right-click the KWH indicator—also known as the Power Consumption indicator—and
00:51
select Indicators > Utilization Settings.
00:54
The Machine Utilization indicator settings appear on the dashboard.
00:58
Next, add station meters for specific operations to the display.
01:03
Begin by hovering the cursor over callout 4, the Planning Station, until the meter displays.
01:10
Right-click and select Optimization > Add Meter to Dashboard.
01:15
Repeat this step for callout 2, the Machining Line, to add its meter to the dashboard.
01:20
Now, adjust the properties of these two operations to see the effect on utilization.
01:25
In the Material Flow Browser, Routings tab, select Planning Station.
01:31
Then, in the Factory Properties browser, Material Flow Object tab, in the Properties section,
01:37
change the Processing Time to 24 minutes.
01:40
Press ENTER.
01:42
Review the results of the change in the Power Consumption indicator and in the layout.
01:47
Note how the percentage of use value decreases and in the layout, the callout for this operation turns from red to green.
01:55
The flag color, based on Utilization Settings, indicates the utilization status of each station.
02:01
Green means well utilized, red means overutilized, and yellow means underutilized.
02:07
Next, adjust the properties of the panel machining operation.
02:11
In the Material Flow Browser, Routings tab, select Operation 3: Panel Machining.
02:17
In the Factory Properties browser, Material Flow Object tab, in the Properties section,
02:24
change the Processing Time to 25 minutes, and then press ENTER.
02:28
Review the results of the change, again noting that the percentage of use value decreases,
02:33
and the callout for this operation turns from red to green.
02:37
Repeat these steps, adding meters for the remaining operations and adjusting the processing time to acceptable levels.
Video transcript
00:04
To optimize the efficiency of your layout in Factory Design,
00:08
you can analyze how each machine is being used within its defined limits.
00:12
Based on the analysis, you can make changes to the layout and review the effects on utilization.
00:18
To follow along with this tutorial, from the Quick Access Toolbar, click Open,
00:23
navigate to the Tutorial 4 folder, and open Material Flow Analysis_Complete.dwg.
00:30
From the ribbon, Factory tab, Material Flow panel,
00:34
expand the Transportation drop-down and select Machine.
00:38
This activates the Machine Utilization Meters.
00:42
If the Machine Utilization indicator is not visible, right-click the KWH indicator—also known as the Power Consumption indicator—and
00:51
select Indicators > Utilization Settings.
00:54
The Machine Utilization indicator settings appear on the dashboard.
00:58
Next, add station meters for specific operations to the display.
01:03
Begin by hovering the cursor over callout 4, the Planning Station, until the meter displays.
01:10
Right-click and select Optimization > Add Meter to Dashboard.
01:15
Repeat this step for callout 2, the Machining Line, to add its meter to the dashboard.
01:20
Now, adjust the properties of these two operations to see the effect on utilization.
01:25
In the Material Flow Browser, Routings tab, select Planning Station.
01:31
Then, in the Factory Properties browser, Material Flow Object tab, in the Properties section,
01:37
change the Processing Time to 24 minutes.
01:40
Press ENTER.
01:42
Review the results of the change in the Power Consumption indicator and in the layout.
01:47
Note how the percentage of use value decreases and in the layout, the callout for this operation turns from red to green.
01:55
The flag color, based on Utilization Settings, indicates the utilization status of each station.
02:01
Green means well utilized, red means overutilized, and yellow means underutilized.
02:07
Next, adjust the properties of the panel machining operation.
02:11
In the Material Flow Browser, Routings tab, select Operation 3: Panel Machining.
02:17
In the Factory Properties browser, Material Flow Object tab, in the Properties section,
02:24
change the Processing Time to 25 minutes, and then press ENTER.
02:28
Review the results of the change, again noting that the percentage of use value decreases,
02:33
and the callout for this operation turns from red to green.
02:37
Repeat these steps, adding meters for the remaining operations and adjusting the processing time to acceptable levels.
How to buy
Privacy | Do not sell or share my personal information | Cookie preferences | Report noncompliance | Terms of use | Legal | © 2025 Autodesk Inc. All rights reserved
Sign in for the best experience
Save your progress
Get access to courses
Receive personalized recommendations
May we collect and use your data?
Learn more about the Third Party Services we use and our Privacy Statement.May we collect and use your data to tailor your experience?
Explore the benefits of a customized experience by managing your privacy settings for this site or visit our Privacy Statement to learn more about your options.