• InfoWater Pro

Running an extended period simulation

Run an extended period simulation.


Tutorial resources

These downloadable resources will be used to complete this tutorial:

iwtr2023M08U01_Running-an-Extended-Period-Simulation.zip

Step-by-step:

Once you are done setting up the hydraulic modeling for an extended period simulation, you can run the simulation.

  1. Open the appropriate .aprx file in ArcGIS Pro.
  2. From the ribbon, InfoWater Pro tab, Project panel, click Initialize.
  3. In the Model Explorer, Attribute tab, click Run Manager.
    The Model Explorer
  1. From the Run Manager dialog box, Standard tab, set Time Setting to EPS, Extended Period Analysis.
  2. Click Run.
    The Run Manager dialog

The green light indicates a successful simulation:

The Run Manager dialog

If this light was yellow, then the simulation would have run partially or completely, and it would have been accompanied by warning messages on the output report. If the run does not run through completely, then those warnings would need to be addressed before running the simulation again until it was successful. All warnings should be reviewed in case they are critical, but some are often negligible.

A red light would indicate that the simulation failed to converge to a solution. Lastly, a gray light would have meant that the simulation did not produce any output, and you would need to troubleshoot to figure out why.

  1. Click OK.
  2. Review the results from the Model Explorer, Attribute tab.
    The Model Explorer