Managing rebar numbers and partitions
Any referenced datasets can be downloaded from "Module downloads" in the module overview.
Manage rebar numbers and partitions - Exercise
In Revit, rebar numbers are added automatically, partitions are not. Partitions indicate what area or
group a bar belongs to.
- Open Revit, then the file MEDICAL CENTER PARKING GARAGE.RVT (or open any Revit project you are working in).
- Go to Level 2.
- Select the Level 2 slab.
- Click on the Reinforcement contextual panel, then click the path button.
- Click the line shown below, then click the flip button to direct the reinforcement into the slab.
- Pick the lines along the edge, as shown below.
- In the Properties, call the Partition West Edge Level 2.
- Click the green Finish checkmark, and you are all set.